# Permitting Speed

How long it takes to get a yes to build one specific thing: a power line, a wind farm, a mine, a factory. Reviews, objections, appeals and court cases can stretch that to many years, often longer than the building itself. In the United States, only a small share of the power plants that asked to join the grid over two decades were ever connected. Yet speed is possible: Germany cut its wait for wind-farm permits by more than a quarter in a single year.

> How long, and how certainly, a specific project gets permission to be built once the rules allow it, measured in months to a decision that holds.

## Maturity
2/5 — Fast where governments chose: Germany cut its average wind permit from 23 to 17 months in one year and built an LNG terminal in under 200 days. Slow almost everywhere else: US environmental reviews take about three years at the median, only 13% of the US grid capacity requested in 2000–2019 reached operation, and major mines took 16.5 years from discovery to production.

Capability 4 · deployment 2 · absorption 3 · bound by regulation · improving

Source: CEQ EIS Timeline Reports (Jun 2020; Jan 2025); LBNL, Queued Up: 2025 Edition; IEA, Electricity Grids and Secure Energy Transitions (Oct 2023); IEA, The Role of Critical Minerals in Clean Energy Transitions (May 2021); Fachagentur Wind und Solar, Status of Onshore Wind Energy Development in Germany 2025; Fiscal Responsibility Act of 2023 (NEPA amendments) (2020–2026)

## What it is
How long it takes, and how certain it is, to get permission to build one specific project once the rules allow it: a power line, a wind farm, a mine, a factory or a housing estate. Measured in months from application to a decision that holds up in court.

## What it does
It sets the delay between deciding to build and building. Every year in review is a year of capital tied up, of costs rising and of the risk that a court sends the project back. For grids and power plants the wait is now often longer than construction, so procedure, not engineering, paces the physical build-out.

## Common misconception
That faster permitting means weaker protection. Much of the delay is sequence and repetition: reviews run one after another, and are then litigated. Germany cut its average wind-permit time by more than a quarter in one year by changing procedure and priority, not by repealing its environmental law.

## Steepens
- The Built-Environment Deficit (the-built-environment-deficit) — large
- Energy Transition and Electrification (energy-transition-and-electrification) — large
- Critical Mineral and Resource Scarcity (critical-mineral-and-resource-scarcity) — moderate
- Distributed and Reshored Manufacturing (distributed-and-reshored-manufacturing) — moderate

## What would change its gradient
- Running reviews in parallel under one lead authority, with a deadline that binds
- Designating zones for grids, renewables and housing in advance, so each project does not re-argue the site
- Short limits on when a decision can be challenged in court