Smart Grids

Smart Grid & Transmission

The power lines, control systems and market rules that move electricity from where it is made to where it is used, and keep supply and demand balanced every second. You can build a solar farm in months; a big new power line can take a decade of permits. In one month, California threw away about 919,000 megawatt-hours of clean power it could not move. Not a shortage of generation: a shortage of grid.

Maturity

3/ 5
measured
BasisThe equipment is mature. Building and connecting it is not: in 2011–2020 the US added about 3,300 circuit-miles of transmission a year within regions and about 70 between them, and new plants now wait more than five years to connect. The delay is procedure, not engineering.SourceE-161, E-162; US DOE, National Transmission Needs Study (Oct 2023); Berkeley Lab, Queued Up: 2026 Edition; FERC Order No. 1920 (13 May 2024)Vintage2011–2026
ReadinessCapability 5Deployment 3Absorption 3Bound byregulationTrendflat

Where it feeds in

4 megatrends in 2 forces

Where you have already met this

California curtailed 919,020 megawatt-hours in a single month in 2025 - electricity generated and thrown away because the system could not absorb it. Not a shortage of generation. A shortage of grid.

If this moved

If connection and permitting ran at the speed of construction, the cheapest generation in history could reach the wires. The map still would not move on this alone: energy transition and climate resilience sit at 1 on consumption norms, and reshoring and the built-environment deficit at 2 on other enablers. It is a paperwork reform with more decarbonisation leverage than most technology programmes.

What to watch for

Interconnection queue length and the time from application to energisation. Transmission projects measured in years from consent, not from groundbreaking.

Not to be confused with

Generation capacity. Announcements are almost always about generation, because you can open a wind farm and you cannot open a permitting reform.

What it is

The wires, control systems and market mechanisms that move electricity and balance supply against demand in real time.

How it works

  1. 01Generation and demand must match, continuouslyElectricity is consumed as it is produced. The grid is a machine for keeping supply and demand equal every second, and frequency is the readout - deviation means the balance is failing.
  2. 02Power flows where physics sends it, not where you route itUnlike data, electricity cannot be addressed. It follows impedance across the whole network, so a new connection changes flows everywhere and every addition needs a study.
  3. 03Connecting a new source or load requires a queue positionThe operator models the effect on the whole network, assigns any reinforcement cost, and issues a connection date. This is where years go - not construction.
  4. 04Variable generation shifts the problem from capacity to flexibilityWith wind and solar the question stops being 'is there enough' and becomes 'can it move fast enough'. Ramping ability, storage and demand response become the scarce goods.
  5. 05When flexibility runs out, energy is discardedCurtailment: generation available and unused. It is the visible symptom of a grid constraint, and it is measured monthly.

State of play

  • California's grid operator curtailed 919,020 MWh of wind and solar in March 2025 alone (CAISO, Key Statistics, Mar 2025).
  • It curtailed 3.4 million MWh across 2024, 29% more than in 2023 (EIA, Today in Energy, 28 May 2025).
  • About 2,060 GW of US generation and storage was waiting in interconnection queues at the end of 2025, 10% less than a year earlier; of the capacity that applied in 2000–2020, 13% was built and 75% withdrew (Berkeley Lab, Queued Up: 2026 Edition).
  • Projects that came online in 2025 took over five years from connection request to operation (Berkeley Lab, Queued Up: 2026 Edition).
  • In 2011–2020 the US energised about 3,300 circuit-miles of new or upgraded transmission a year within regions, and about 70 a year between regions (US DOE, National Transmission Needs Study, Oct 2023).
  • FERC's Order No. 1920 (13 May 2024) requires transmission planning at least 20 years ahead; legal challenges to it are on hold at the Fourth Circuit (FERC; Harvard EELP regulatory tracker, 2026).

Why it matters

It is the binding constraint on electrification in most developed markets - not generation, not storage, but the ability to connect and move power.

  • Generation stopped being the constraint on the energy transition. The grid became it, and almost no public discussion has caught up.
  • It is the clearest case in the Compendium where the technology enabler is mature and a government-clock enabler is the minimum - the equipment exists, the permitting does not.
  • Interconnection reform is a paperwork intervention with more decarbonisation leverage than most technology programmes, which is exactly why it is under-funded: you can open a wind farm and you cannot open a permitting reform.

What holds it back

Interconnection queue length

The binding one. Studies are sequential, speculative projects clog the queue, and operators are staffed for a slower era.

Transmission permitting and consent

A line takes about a decade in most jurisdictions and most of that is not construction. Routes cross jurisdictions with veto points and no shared timetable.

Market rules written for dispatchable plant

Priority dispatch and cost-recovery structures insulate inflexible generators from competitive signals, so flexibility is under-rewarded exactly where it is scarce.

Demand arriving faster than planning assumed

Electrified heat and transport plus data centres land on a planning process built around a demand profile that no longer applies.

Terms

Curtailment
Generation that was available and deliberately not used, because the system could not absorb or move it. Measured in MWh and published monthly by most operators.
Interconnection queue
The ordered list of projects awaiting a connection study and a grid connection date. Queue position, not construction, is what usually determines when a project can exist.
Dispatchable
Generation that can be turned up or down on command. Wind and solar are not; the value of dispatchability rises as their share rises.
Priority dispatch
A rule requiring certain plants to run regardless of price. It reserves network headroom and is a documented cause of renewable curtailment.
Ramping
How fast output can change. As variable generation grows, ramping ability becomes scarcer and more valuable than raw capacity.

Steepens

The gradient behaves like a sticky rubber band: it is pulled hardest toward the weakest enabler. Marginal links are shown but do not pull.

If this moved one step

Computed from the map as it stands: this score raised from 3 to 4, every other score unchanged. It is arithmetic, not a forecast.

Raised one step on its own, it lifts no megatrend's weakest link; each gradient it feeds still rises a little.

The gradient also rises in

What if it moved?

What would change the gradient

Conditional, not predictive. No dates, no probabilities.

  1. 01Interconnection queue reform, which is the highest-leverage and least photogenic lever available
  2. 02Permitting timelines for transmission
  3. 03Demand flexibility, which reduces the amount of grid that has to be built

Common misconception

That grid limits are technical. Permitting, planning and interconnection process are the dominant delays, and they are institutional rather than engineering problems.

Talin, B. (2026). Smart Grid & Transmission. The Future Explorer, dataset v0.4.0 (2026-11-16). https://explorer.talin.digital/e/smart-grid-and-transmission/

Smart Grid & Transmission: maturity 3/5